DELIVERY PRACTICE · Protected power
A complete supply of UPS systems, battery modules and maintenance bypass equipment sized for the actual load, required runtime and service conditions.
Initial situation
UPS units were isolated, batteries had different remaining life and actual runtime had never been tested under working load.
Architecture
Load-profile and power-quality measurement
Modular N+1 UPS with maintenance bypass
Matched battery strings and monitoring
Load tests and emergency procedures
Solution scope
Measured outcomes
Engineer’s comment
Runtime was validated by a post-installation load test, turning a calculated value into a verified operating parameter.
Customer testimonial
We can see every module and battery string, while maintenance uses bypass without shutting down equipment.